
STEP 4 - Curing the inner skin of carbon fibre
Before the core of the component was added, the carbon was cooked
whilst under vacuum to cure the resin. This was a key stage
and so it was closely monitored by the build team. The structure
was cured at 65 degrees C.
STEP 5 - Adding the middle layer (the
core)
A layer of glue film was applied to the inner skin of carbon,
and the core, a 10mm thick pvc foam, laid directly onto the
film.
STEP 6 - Adding final
layer of carbon
A final outer layer of carbon fibre was applied following
a similar process to that in steps four and five.
STEP 7 - Painting the boat
The
team faired the boat (sanded) until they had a smooth surface
to work on.Two undercoats of Blakes epoxy primer undercoat
(EPU) were then applied. In her early days, the boat was black,
but for her debut at the London Boat Show 2000, she was painted
yellow.
STEP 8 - Popping the components out of the plugs
We're nearly there now. One of the final steps in the build
of the rowing boat was to pop the boat off the plug and carry
out a detailed inspection. The team used straps and pulleys
to ease the boat off the plug, and place it on cradles, where
the rest of the work was done.
With all the components completed, the team carried on with
fitting them together to form the finished structure. Carbon
fibre tapes were pre-cut and coated with epoxy resin. The
tapes were gently placed where joins needed to be made.
STEP 9 - Weighing the boat
Time to weigh the boat. By weighing the boat, the team can
check its centre of gravity.
STEP 10- Painting the boat
When the boat was structurally complete, joints were faired
in preparation for Blakes EPU. Following the EPU, the final
gloss coat was applied.
STEP 11 - Fitting the equipment
All of the rowing, communications and navigation equipment
the team will need to stay safe, and keep everyone on land
on top of what is happening while they are at sea will be
fitted.
STEP 12 - Sea trials!
|